  • Burn-Up Chart: A Complete Guide With Examples

Burn-Up Chart: A Complete Guide With Examples

     56 views

Burn-up chart img

Burn-up chart – Key takeaways

  • A burn-up chart tracks completed work over time.
  • It also tracks the project’s total scope.
  • This makes scope changes easier to identify.
  • Burn-down charts focus on remaining work.
  • The burn-up vs burn-down chart distinction is simple.
  • Burn-up shows work completed.
  • Burndown shows work remaining.
  • A Jira burndown chart supports sprint-level tracking.
  • Burn-up charts are useful for releases and projects.
  • Neither chart should replace project discussions.
  • Both work best alongside backlog and delivery data.

What is a burn-up chart?

A burn-up or burnup chart is widely used in agile project management. It is a visual project management graph that tracks project progress.
The a burn-up chart generally contains two lines:
  • Completed work line, which moves upward as work gets completed.
  • Scope line, which represents the total amount of planned work.
Here’s a visual representation of what a burn-up chart looks like in project management –
burn up chart
The horizontal axis represents time. The vertical axis represents work. Depending on the project, work might be measured in:
  • Story points
  • Tasks
  • User stories
  • Features
  • Hours
  • Backlog items
For example, a scrum team has 120 story points planned for a release.
t the beginning, completed work is zero. As the team finishes stories, the completed-work line increases. If new stories are added, the scope line increases. When completed work reaches the current scope, the tracked work is complete.
Now that we have a clear understanding on what a burn-up chart. Let’s understand how does a burn-up chart work.

How does a burn-up chart work?

A burn-up chart works by plotting project data across time, the process is relatively straightforward. First, the team defines the initial scope. Then, the team has to select a consistent unit for measuring work.
Next, the team has to record all the completed work at regular intervals.
The team then records completed work at regular intervals. It also records changes to the total scope. These values create two lines on the chart.

Example

Consider this five-sprint project.
Sprint Completed Work Total Scope
Sprint 1 15 100
Sprint 2 32 100
Sprint 3 50 115
Sprint 4 78 115
Sprint 5 105 125
Sprint 6 125 125

Several things are visible here. The team completed work consistently.

However, the project scope here has increased twice. It first increased from 100 points to 115 points. Later, it increased from 155 points to 125 points.
If you only look at the completed work, you will most probably miss the scope movement. The burn-up chart provides that missing additional context.

What does a burn-up chart show?

In a burn-up chart, you usually can see four important things. Those are explained below.

1. Completed work

The completed-work line shows how much work is finished. The line generally moves upward. A flat section indicates that no additional work was completed during that period.

2. Total scope

The scope line shows the amount of work currently planned. This line does not necessarily stay flat. New requirements can increase it. Removed requirements can decrease it.

3. Progress toward completion

The distance which is there between the “completed” work and “total scope” represents the unfinished work.
For instance –
  • Total scope = 100 story points
  • Completed = 70 story points
  • Remaining = 30 story points
The chart makes this gap easy to understand.

4. Scope changes

Scope movement is one of the most useful features. If the scope line rises, more work enters the project. If it falls, work was removed or re-estimated. This distinction helps teams explain changes in delivery dates.
Next, there are a few basic components in a burn-up chart. Just like a bar or column graph. In the next section, we can see what the burn-up chart components are.

Burn-up chart components

A burn-up chart has several basic graph-like components, which will be explained below. Understanding the components will make the chart easier for you to interpret.

X-axis

The x-axis represents time.
Which shows:
  • Days
  • Weeks
  • Sprints
  • Releases
  • Project phases
In a sprint-level chart, you may make sprint 1, sprint 2, and sprint 3. A daily chart can be used as individual calendar dates.

Y-axis

The y-axis measures work. The measurement depends on how the team estimates work. The important factor is being consistent.

Completed work line

This line begins near zero. It rises whenever the team completes work. A steep increase indicates faster completion during that period. A flat section indicates little or no completed work. The line should always be interpreted within the project context.

Scope Line

The scope line represents total planned work. It provides context for the completed-work line. A rising scope line indicates additional work. A falling scope line indicates reduced scope.
Let’s look at an example to understand more

Burn-up chart example

Consider a software team developing a customer portal. The initial backlog contains 200 story points. The team plans six sprints.
The project data looks like this:
Sprint
Completed Points
Total Scope
Sprint 1 30 200
Sprint 2 65 200
Sprint 3 95 220
Sprint 4 130 220
Sprint 5 170 240
Sprint 6 215 240
At first, the team planned 200 points. After Sprint 2, the team completed 65 points. During Sprint 3, the scope increased by 20 points. Later, another 20 points were added to the backlog. By Sprint 6, the team completed 215 points. However, the project scope reached 240 points.
So the project still has:
240 − 215 = 25 story points remaining.

What is scope creep in a burn-up chart?

Scope creep occurs when any sort of additional work enters a project – without corresponding adjustments to the original plan. Maintaining a burn-up chart makes it easier to identify this.
Scope creep in burn-up chart example –
The original scope is 100 story points. The team completes 40 points, and the stakeholders then add 30 more points. The scope now becomes 130 points.
The team still has 90 more points remaining.
Without tracking scope separately, stakeholders will just see that the team has completed “40 points” and will assume the project is progressing towards the original target, which was 100 points.
The scope line in the burn-up chart provides the missing context. However, not every scope increase is necessarily negative. Usually, agile projects change requirements based on feedback. The important point is to distinguish planned scope changes from unexpected scope expansion.

Burn-up vs burn-down chart

Burn-up and burn-down charts both track agile progress. Their primary difference is how they represent work. A burn-up chart shows work completed. A burn-down chart shows work remaining. Consider a project with 100 story points. After completing 25 points:
  • Burn-up: 25 points completed.
  • Burn-down: 75 points remaining.
The underlying progress is identical. The visual interpretation differs. The burn-up vs. burndown chart comparison becomes clearer when you look at what each chart answers.
Question
Burn-up
Burndown
How much work is completed? Directly visible Indirectly visible
How much work remains? Calculated from scope Directly visible
Did project scope change? Clearly visible Less obvious
Can stakeholders see scope movement? Yes Limited
Is progress easy to understand? Yes Yes
Useful for sprint tracking? Yes Yes
Useful for release tracking? Yes Yes
Number of main lines Usually two Usually one
Scope transparency High Lower
The choice depends on what the team needs to communicate.

Burn-up chart vs burndown chart example

Let’s consider a project with an initial scope of 100 points, and the project team completes 20 points. Then five points are removed; later, 15 points are added.
After calculating everything, the final scope becomes 110 points. Suppose the team then completes 50 points.
A burn-up chart would show:
  • Initial scope: 100
  • Scope reduction: 95
  • Scope increase: 110
  • Completed work: 50
The burndown would mainly show remaining work. At 50 completed points against 110 current scope: Remaining work = 60 points. The burn-up chart provides more information about why that number changed.

How to create a burn-up Chart

You can create one using spreadsheet software. Excel and Google Sheets both work well.
Start with three columns:
Sprint
Completed Work
Total Scope
1 15 100
2 30 100
3 48 110
4 70 110
5 92 120
6 120 120
Then create a line chart. Use:
  • Sprint as the horizontal axis
  • Story points as the vertical axis
  • Completed work as one series
  • Total Scope as another series
The resulting chart becomes a basic burn-up chart.

Burn-up chart vs cumulative flow diagram

These charts are sometimes confused. A burn-up chart tracks completed work against scope. A cumulative flow diagram shows work across workflow states.
Burn up chart vs cumulative chart
For example:  Having a cumulative flow diagram helps identify workflow challenges. A burn-up chart focuses on overall completion. They answer different project management questions.

Conclusion

Burn-up charts work well across agile projects. They support sprint tracking, release planning, and forecasting. It is important for project professionals to understand tools like burn-up charts. These tools help PMP aspirants and professionals pursuing PMP certification who are familiar with project management tools.
It connects project management concepts with how teams manage delivery in practice.

FAQs regarding burn-up charts

Here are some commonly asked questions on burn-up charts in project management.

1. What is a burn-up chart in agile?

A burn-up chart tracks completed work against total project scope. Agile teams use it to monitor progress and identify scope changes.

2. What is the difference between burn-up and burndown?

A burn-up chart shows completed work increasing over time. A burndown chart shows remaining work decreasing toward zero.

3. What does a burn-up chart show?

It usually shows completed work and total scope. The two lines help teams understand progress and scope movement.

4. Why does the scope line increase on a burn-up chart?

The scope line increases when additional work enters the tracked project scope. This could involve new requirements, features, or backlog items.

5. Can a burn-up chart show scope creep?

Yes. A rising scope line shows that planned work increased. Teams should still determine whether the change was planned or unexpected.

6. Is burn-up better than burndown?

The charts emphasize different information. Burn-up charts show completed work and scope. Burndown charts focus on remaining work.

Previous Post

Next Post

Back To Top Button

 

 

 

 

Upcoming PMP Batches

Batch Name
Date & TimeDetails
November Batch (4 Days – Weekend) – PMP Online

14th, 15th, 21st & 22nd November 2026 Time: 8:00am to 6:00pm, ISTKnow More